MassDOT is holding a public meeting on July 11 about the very exciting Bowker overpass reconstruction projects.
Bowker Overpass
Reconnect Parkland through Storrow Project
MassDOT has opened a public conversation about the reconstruction of Storrow Drive East Bound near Kenmore Square where it intersects with the Bowker Overpass.
7/19/16 Bowker Update
MassDOT has passed along the following status update on the Bowker Overpass construction: Demolition – has been completed Lighting under the bridge – Based on a site walk with Senator Brownsberger, Representative Rushing, and Representative Livingstone we have added a new lighting system to the project. This work will begin in August and will be …
Charlesgate Park Update
Comment from Will B. There have been a number of personnel changes that have complicated our efforts to nail down plans for the park improvements, but Highway Commissioner Tom Tinlin and the new DCR Commissioner Leo Roy are getting closer to an understanding of how to move forward. Senator Brownsberger and Representative Rushing recently met with the …
12/11/15 Bowker Overpass Construction Schedule Update
MassDOT has provided this updated construction schedule for the work that is currently underway on the Bowker Overpass. The work on the travel lanes has proceeded from west to east. (Note from Will: the phasing for this project is straightforward and, while the schedule has slid a few months, the basic plan has not changed.)
Bowker Overpass Repairs Update
The Bowker Overpass Repair Project is moving towards completion. Phase 4 demolition started last week and will continue into December on the western lane of the northbound side of the overpass. This is the final phase of demolition, which has been the noisiest and most disruptive work for neighbors. The repair project is expected to be complete by summer of 2016.